You searched for VC+Summer+3 and we found approximately 19 results.Below we are displaying search results 1 to 10


Vogtle 3 shield building takes shape

Located in: New Nuclear

20 August 2015

Vogtle 3 building panel installation 48The installation of shield building panels has begun at the first AP1000 unit under construction at the Vogtle plant in Georgia, USA. The shield building encases the unit's containment vessel.

Major lift for Vogtle 3

Located in: New Nuclear

11 August 2015

Vogtle_3_CA01_lift_(Georgia_Power)_48US nuclear construction at Vogtle has reached another milestone with the lifting of Vogtle 3's CA01 module into place.

Major module installed at Summer 3

Located in: New Nuclear

08 July 2015

Summer 3 reactor vessel cavity installation 48The module that will house the reactor pressure vessel of the second AP1000 unit under construction at the VC Summer site in South Carolina has been installed. Meanwhile, the reactor vessel itself has been delivered to the site.

Regulatory filing tracks Summer progress

Located in: New Nuclear

18 May 2015

Summer_2_steam_generator_Jan_15_(SCE&G)_48South Carolina Electricity & Gas (SCE&G) expects a further 52-day delay to the 'substantial completion' date for VC Summer unit 2, although unit 3 looks to be slightly ahead of schedule according to its latest regulatory filing.

Summer ownership decided

Located in: Corporate

28 January 2014

Summer 3 concrete (SCE&G)_48South Carolina Electricity and Gas (SCE&G) is to increase its ownership of two nuclear units under construction at VC Summer in South Carolina. Duke Energy has said that it is no longer looking to acquire a stake in the project.

Carolinas appreciate nuclear's true worth

Located in: Corporate

21 November 2013

Summer 3 first concrete 48The total economic impact of the nuclear industry in North and South Carolina has been estimated to exceed at least $20 billion per year in a detailed study carried out by a team at Clemson University.

Second Summer AP1000 under construction

Located in: New Nuclear

06 November 2013

Summer 3 first concrete 48Safety-related concrete has been poured for the basemat of the second AP1000 unit at the VC Summer plant in South Carolina. It comes seven months after the same milestone for the first unit there.

Mississippi electric supplier eyes share in Summer

Located in: Corporate

16 April 2012

Summer 2 and 3 78x48A wholesale electricity supplier in Mississippi is in discussions with Santee Cooper about buying a share of the output from the two reactors under construction at the VC Summer plant in South Carolina. South Mississippi Electric Power Association is also considering buying a portion of Santee Cooper's 45% ownership interest in the new units.

Regulator OKs the start of Summer

Located in: New Nuclear

02 April 2012

Summer 2 and 3 78x48Two AP1000 reactors at the VC Summer plant in South Carolina are to be the second US new-build project to receive combined construction and operation licences after receiving the final regulatory go-ahead.

Agreement on Summer cost overruns

Located in: New Nuclear

30 March 2012

Summer 2 and 3 78x48South Carolina Electric & Gas has signed a preliminary agreement with Westinghouse and the Shaw Group to settle a dispute over early cost overruns for the construction of two AP1000 units at its VC Summer plant. A delay in receiving a licence for the units has led to a rescheduling of their completion dates.


1 2