Summer ownership decided

Located in: Corporate

28 January 2014

Summer 3 concrete (SCE&G)_48South Carolina Electricity and Gas (SCE&G) is to increase its ownership of two nuclear units under construction at VC Summer in South Carolina. Duke Energy has said that it is no longer looking to acquire a stake in the project.

Carolinas appreciate nuclear's true worth

Located in: Corporate

21 November 2013

Summer 3 first concrete 48The total economic impact of the nuclear industry in North and South Carolina has been estimated to exceed at least $20 billion per year in a detailed study carried out by a team at Clemson University.

Second Summer AP1000 under construction

Located in: New Nuclear

06 November 2013

Summer 3 first concrete 48Safety-related concrete has been poured for the basemat of the second AP1000 unit at the VC Summer plant in South Carolina. It comes seven months after the same milestone for the first unit there.

Mississippi electric supplier eyes share in Summer

Located in: Corporate

16 April 2012

Summer 2 and 3 78x48A wholesale electricity supplier in Mississippi is in discussions with Santee Cooper about buying a share of the output from the two reactors under construction at the VC Summer plant in South Carolina. South Mississippi Electric Power Association is also considering buying a portion of Santee Cooper's 45% ownership interest in the new units.

Regulator OKs the start of Summer

Located in: New Nuclear

02 April 2012

Summer 2 and 3 78x48Two AP1000 reactors at the VC Summer plant in South Carolina are to be the second US new-build project to receive combined construction and operation licences after receiving the final regulatory go-ahead.

Agreement on Summer cost overruns

Located in: New Nuclear

30 March 2012

Summer 2 and 3 78x48South Carolina Electric & Gas has signed a preliminary agreement with Westinghouse and the Shaw Group to settle a dispute over early cost overruns for the construction of two AP1000 units at its VC Summer plant. A delay in receiving a licence for the units has led to a rescheduling of their completion dates.

Westinghouse secures AP1000 approval

Located in: New Nuclear

23 December 2011

AP1000 cutawayAmerican nuclear safety regulators have approved an amendment to the AP1000 reactor design, in a major step towards US deployment of the model. Construction on new reactors could begin very soon.

Duke eyes stake in new Summer units

Located in: Industry Talk

21 July 2011

Duke Energy has signed a letter of intent with Santee Cooper to negotiate a potential minority stake in Santee Cooper's 45% ownership of the two new reactors planned at the VC Summer nuclear power plant in South Carolina. The letter calls for Duke to take a 5%-10% stake of the capacity and output from the new units (about 10%-20% of Santee Cooper's ownership interest in them). This would represent a share in generating capacity of between 25 and 50 MWe from each reactor. Santee Cooper said it signed a similar letter of intent in March 2011 with Florida-based Orlando Utilities Commission for a similar proportionate share of the capacity and output from the two units. The remaining 55% of the new Summer units is owned by South Carolina Electricity & Gas (SCE&G). Summer units 2 and 3 - both AP1000 reactors - are scheduled to begin operating in 2016 and 2019, respectively. Duke said that it continues work on development activities for its proposed two AP1000s at the new William States Lee site in South Carolina.

Reactor projects continue to advance

Located in: New Nuclear

04 March 2011

STP 3 and 4 (STPNOC)Two projects to build new nuclear reactors in the US have moved forward with the completion of the final environmental impact statement for South Texas Project units 3 and 4 and the award of a contract to upgrade transmission lines at VC Summer.

Pike wins switchyard contract for new US units

Located in: Corporate

10 November 2009

VC Summer 2 and 3 (NRC)The Shaw Group has awarded an engineering, procurement and construction contract for a new transmission switchyard and offsite power system for its planned new reactors at the VC Summer power station in South Carolina to Pike Electric Corporation.