Russia installs reactor pressure vessel at Belarus plant
Monday, 3 April 2017
Atomstroyexport (ASE) announced today it has installed the reactor pressure vessel (RPV) of unit 1 of the nuclear power plant under construction at Ostrovets in Belarus. The RPV, which weighs more than 330 tonnes, is 11 meters long and 4.5 meters in diameter, was placed in position at 8.30pm on 1 April.
Before the installation operation, the RPV of the VVER-1200 unit passed an inspection by ASE and the Belarusian Nuclear Power Plant Company that found the equipment met all regulatory requirements. The installation itself was carried out in two stages: the RPV was lifted on to a transport gantry and moved to the central chamber on rails; a polar crane then placed the vessel into a vertical position and then on the bearing ring inside the reactor pit.
Vitaly Medyakov, vice president of the Belarusian project at AO NIAEP, part of the ASE Group, said installation of the RPV had required “pinpoint precision”. “Since the bearing ring carries all the weight, the axis of the reactor pressure vessel and the bearing ring cannot deviate from each other by more than one millimetre,” he said.
Sergey Olontsev, senior vice president of Russian projects in the ASE Group, added that an installed RPV is the “reference point” for installing the main circulation equipment of a reactor unit.”
ASE Group was formed by the merger of Russian state nuclear corporation Rosatom’s engineering subsidiaries, including, Atomstroyexport, Atomenergoproekt and Atomproekt.
AEM-Technology, another Rosatom subsidiary, said in May last year it had completed assembly of the reactor vessel for the VVER-1200 unit 2 of the Belarus nuclear power plant.
The RPV for unit 1 was shipped to the construction site in October 2015, but workers dropped it during installation work in August last year. Rosatom subsidiaries OKB Gidropress and Atomstroyexport carried out an inspection of the RPV and sent the results of that to the project's customer - the Belarusian Nuclear Power Plant Company - and to Gosatomnadzor, specifically, the Nuclear and Radiation Safety Department of the Belarusian Emergencies Ministry. Although the RPV was found to be "absolutely functional”, Rosatom’s then director-general Sergey Kirienko agreed to a replacement and at no additional cost to the customer, other than for its transport to the site.
An intergovernmental agreement between Russia and Belarus specifically on cooperation in the construction of a nuclear power plant in Belarus was signed in March 2011.
Operation of the first unit of the Ostrovets plant is scheduled for November 2018 and the second unit in July 2020, to give 2340 MWe net capacity on line.
Before the installation operation, the RPV of the VVER-1200 unit passed an inspection by ASE and the Belarusian Nuclear Power Plant Company that found the equipment met all regulatory requirements. The installation itself was carried out in two stages: the RPV was lifted on to a transport gantry and moved to the central chamber on rails; a polar crane then placed the vessel into a vertical position and then on the bearing ring inside the reactor pit.
Vitaly Medyakov, vice president of the Belarusian project at AO NIAEP, part of the ASE Group, said installation of the RPV had required “pinpoint precision”. “Since the bearing ring carries all the weight, the axis of the reactor pressure vessel and the bearing ring cannot deviate from each other by more than one millimetre,” he said.
Sergey Olontsev, senior vice president of Russian projects in the ASE Group, added that an installed RPV is the “reference point” for installing the main circulation equipment of a reactor unit.”
ASE Group was formed by the merger of Russian state nuclear corporation Rosatom’s engineering subsidiaries, including, Atomstroyexport, Atomenergoproekt and Atomproekt.
AEM-Technology, another Rosatom subsidiary, said in May last year it had completed assembly of the reactor vessel for the VVER-1200 unit 2 of the Belarus nuclear power plant.
The RPV for unit 1 was shipped to the construction site in October 2015, but workers dropped it during installation work in August last year. Rosatom subsidiaries OKB Gidropress and Atomstroyexport carried out an inspection of the RPV and sent the results of that to the project's customer - the Belarusian Nuclear Power Plant Company - and to Gosatomnadzor, specifically, the Nuclear and Radiation Safety Department of the Belarusian Emergencies Ministry. Although the RPV was found to be "absolutely functional”, Rosatom’s then director-general Sergey Kirienko agreed to a replacement and at no additional cost to the customer, other than for its transport to the site.
An intergovernmental agreement between Russia and Belarus specifically on cooperation in the construction of a nuclear power plant in Belarus was signed in March 2011.
Operation of the first unit of the Ostrovets plant is scheduled for November 2018 and the second unit in July 2020, to give 2340 MWe net capacity on line.
Most Read

Mars in 30 days? Russia unveils prototype of plasma rocket engine
Friday, 7 February 2025

Nuclear 'a great field for students or people with trades to go into'
Wednesday, 25 September 2024

Argentina ramping up radioisotope production
Tuesday, 22 October 2024

The fluorescent mosquitoes helping to tackle diseases
Monday, 11 November 2024
Podcasts & Features
Podcast: The World Bank ends ban on nuclear energy funding
Podcasts & Features Saturday, 28 June 2025
Podcast: World Nuclear Supply Chain conference
Podcasts & Features Wednesday, 18 June 2025
