Earlier this year the US Nuclear Regulatory Commission (NRC) formally accepted for review Orano Enrichment USA's application for a licence to authorise possession and use of special nuclear material at the proposed Project IKE uranium enrichment facility. The regulator set an accelerated 12-month review schedule, eyeing completion of the process by 30 April 2027.
The revised schedule is set out in a letter to Orano dated 27 October after the company asked for more time to submit responses to Requests for Additional Information - or RAIs - issued by the regulator in relation to the application.
Orano USA announced in September 2024 its selection of Oak Ridge in Tennessee as its preferred site for a new centrifuge uranium enrichment facility. After pre-application engagement with the NRC, the company submitted its environmental report for the project in January this year, and its application in March.
The licensing effort leverages the licensing application from the Eagle Rock Enrichment Facility, a centrifuge plant Orano's forerunner company Areva had previously planned to build at Idaho Falls. The NRC issued a licence in 2011 for Eagle Rock, but the licence was terminated - at the request of the company - in 2018.
"The original accelerated review schedule was based on assumptions that Orano would provide complete and timely responses to NRC's RAIs and provide a detailed crosswalk comparing the Project IKE application to the previously approved Eagle Rock Enrichment Facility licence which Orano asserted would share some similarities to Project IKE," the NRC said in its 27 October letter to the company. "The crosswalk was not provided, which limited the NRC review team's ability to leverage the precedent from the Eagle Rock safety evaluation. Additionally, the staff has found in its review that there are limited similarities between the Project Ike and Eagle Rock applications that could be leveraged to expedite its review."
Orano has told the NRC it expects to submit all RAI responses by 14 December, and, based on Orano’s revised response schedule, the NRC says it now anticipates completing the review of the application by 20 June 2027. The regulator says its staff will "continue to perform review activities and concurrence processes in parallel and will maintain accelerated review schedules for individual technical areas" as far as is practicable.
An Orano spokesperson has told the American Nuclear Society's Nuclear News that the extended review time is not expected to delay the start of enrichment operations, expected in 2031.