First concrete for US advanced reactor
Kairos Power has announced the start of installation of nuclear safety-related concrete marking the start of "nuclear construction" for the Hermes Low-Power Demonstration Reactor project in Oak Ridge, Tennessee.
_70169.jpg)
Kairos broke ground for the scaled demonstration of its KP-HFR fluoride salt-cooled high-temperature reactor technology last July, with excavation works completed in October. Safety-related construction activities, which are subject to oversight from the US Nuclear Regulatory Commission (NRC), formally began on 1 May, with the start of work on the the piers that will form part of the building's foundation. Hermes will have 51 such piers, which are six feet (just under 2 metres) in diameter and will extend about 40 feet below ground, anchoring the building to bedrock.
Kairos Power CEO and co-founder Mike Laufer described the first safety-related concrete pour for a US advanced reactor under an NRC construction permit as a major milestone. "This achievement reflects the value of our iterative development process to meet the necessary nuclear quality standards and provide crucial real cost information that gives confidence to our customers. It is a testament to the hard work of our dedicated team and represents an enormous amount of learning and progress," he said.
An auger drills the pier (Image: Kairos)
The concrete pour was the culmination of several months of preparation, Kairos said, coming after programmes to test the drilled pier installation process and refine the company's nuclear quality assurance programme. A full-scale test pier was completed in November, and 70 piers have now been drilled for Kairos Power's ETU 3.0 non-nuclear engineering test unit, which is being built adjacent to the Hermes site as part of Kairos's iterative approach for the development of its KP-FHR technology. It says this has enabled the team, led by Barnard Construction Company, Inc, to become proficient at installing piers using quality control checklists similar to those that will be used for Hermes.
Quality checking rebar for the pier (Image: Kairos)
The Hermes reactor will use tri-structural isotropic (TRISO) uranium fuel and a mixture of lithium fluoride and beryllium fluoride salts known as Flibe as its coolant. This combination yields robust inherent safety while simplifying the reactor's design, Kairos said.
Hermes, which is supported by risk reduction funding from the US Department of Energy's Advanced Reactor Demonstration Program, is the first non-light-water reactor to be permitted in the USA in more than 50 years. It will not produce electricity, but Hermes 2 - a two 35 MWt-unit plant for which the US Nuclear Regulatory Commission issued a construction permit in November - will include a power generation system. The commercial deployment of the reactor is supported by a power purchase agreement signed with Google in October 2024, for power from a fleet of up to 500 MW of capacity by 2035.
Article researched and written by WNN's Claire Maden
_92619.jpg)

_84504.jpg)

